Advertisement

"The budget for this project was entirely wrong..."

The report by consultants PWC into the skyrocketing cost overruns of the National Children’s Ho...

Share this article

18.32 10 Apr 2019


"The budget for this project was entirely wrong..."


Listen to this episode


Share this article

18.32 10 Apr 2019


The report by consultants PWC into the skyrocketing cost overruns of the National Children’s Hospital has found a “series of weaknesses” involving initial planning, budget oversight and execution of the project.The report was commissioned into the rising costs of the hospital earlier this year, and tasked with finding out who knew what, and when about the cost of the project spiralling to what is an estimated €1.7 billion.

Dr. Paul Davis a lecturer in DCU who works in the area of public procurement and Tom Parlon Director General of the Construction Industry Federation join Ivan to discuss their opinion on where the project has gone wrong.


Related Episodes

What is a presidential library...

00:11:51

What is a presidential library, and will Trump build his own ?

The Pat Kenny Show

00:11:51


Why do rich countries continue...

00:16:32

Why do rich countries continue to fail in delivering infrastructure and services for their citizens?

The Pat Kenny Show

00:16:32


The dangers of buying weight-l...

00:14:12

The dangers of buying weight-loss injections online, and why your pharmacist may now be your first stop for healthcare advice.

The Pat Kenny Show

00:14:12


Is AI coming for your job ?

00:13:06

Is AI coming for your job ?

The Pat Kenny Show

00:13:06