"The budget for this project was entirely wrong..."

The report by consultants PWC into the skyrocketing cost overruns of the National Children’s Hosp...

Share this article

18.32 10 Apr 2019


"The budget for this project was entirely wrong..."


Listen to this episode


Share this article

18.32 10 Apr 2019


The report by consultants PWC into the skyrocketing cost overruns of the National Children’s Hospital has found a “series of weaknesses” involving initial planning, budget oversight and execution of the project.The report was commissioned into the rising costs of the hospital earlier this year, and tasked with finding out who knew what, and when about the cost of the project spiralling to what is an estimated €1.7 billion.

Dr. Paul Davis a lecturer in DCU who works in the area of public procurement and Tom Parlon Director General of the Construction Industry Federation join Ivan to discuss their opinion on where the project has gone wrong.


Related Episodes

360 Years On: The Great Fire o...

00:52:24

360 Years On: The Great Fire of London

Talking History With Patrick Geoghegan

00:52:24


Mladic’s death and Bosnia’s un...

00:09:15

Mladic’s death and Bosnia’s unhealed wounds

The Pat Kenny Show

00:09:15


Knife-edge Iceland referendum:...

00:14:57

Knife-edge Iceland referendum: EU talks rejected

The Pat Kenny Show

00:14:57


Pat's Sunday Paper Review...

00:17:20

Pat's Sunday Paper Review August 30th

The Pat Kenny Show

00:17:20